HVOF RUNNING COSTS
Dear all,
I would like to know what are the factors to be considered while calculating running cost of liquid fuel hvof system for estimation of jobs I know that labour cost will vary as per region but i want to get a generlised Information Thanks Vijay Deshpande |
|||
|
06-24-2008, 12:30 AM
Post: #2
|
|||
|
|||
|
RE: HVOF RUNNING COSTS
Hi Vijay
To estimate spraying costs you need to get "coverage" (m2/hr/0.1mm) and "powder required" (kg/m2/0.1mm) data for your specific powder and spray parameters. Failing that, deposit efficiency, spray rate and coating density can be used. From this and the surface area of the job and coating thickness desired you can estimate how much powder and time is required for spraying (allow a lttle extra for idle time, spraying off job etc.). From the time estimate you can then estimate things like consumption of labour, kerosine, oxygen, air, cooling water, electricity etc. Obviously, costing of associated process like cleaning, blasting, masking, sealing, finishing etc. are not included here. Probably, not what you wanted, but I don't have the time or space to go into much detail. If you have any specific areas you are having trouble estimating, let us know. Your equipment manuals may have information regarding estimating costs.
Regards Gordon |
|||
|
« Next Oldest | Next Newest »
|
| Possibly Related Threads... | |||||
| Thread: | Author | Replies: | Views: | Last Post | |
| RUNNING COST COMPARISON BETWWEN D GUN AND HVOF SYSTEMS | vijaydeshin | 1 | 572 |
12-17-2007 01:34 AM Last Post: Gordon |
|

SEF Portal
Search Archives
Member List
Calendar
Help




Probably, not what you wanted, but I don't have the time or space to go into much detail. If you have any specific areas you are having trouble estimating, let us know. Your equipment manuals may have information regarding estimating costs.